Cabinets & Countertops in Westminster, CA: What the Job Actually Costs
Cabinet and countertop work in Westminster runs $14,000 – $45,000 for a full kitchen set, or $4,000 – $13,000 for cabinets alone and $2,000 – $6,500 for counters, with most jobs taking two to four weeks from demo to final caulk. That range holds for a typical Bolsa Avenue-area tract home with original 1970s boxes and a straight run of cabinets. Call (833) 522-5059 and we’ll walk you through what your kitchen is likely to need before anyone shows up.
How the job runs, day by day

Cabinet and countertop work is a sequence, not a single install day. Skipping a step shows up six months later as a door that rubs or a counter seam that lifts. Here’s the order we hold to.
Stage 1: Site check and templating decision (day 1, about 2 hours)
We pull existing cabinet doors and drawer fronts, check wall plumb, and confirm whether the boxes are square enough to reface or need full replacement. You decide at this point: reface or replace. If your cabinets are 1990s particleboard with water damage under the sink, replace. Solid 1970s plywood boxes often take refacing well. This is also when we measure for countertop templating, which happens after cabinets are set, not before.
Stage 2: Demo and prep (days 2 – 4)
Old cabinets come out, and this is where Westminster surprises show up. A large share of homes here were built between 1950 and 1975, and pulling boxes often exposes galvanized supply lines, knob-and-tube wiring with no ground, or drywall that crumbles at the fastener line. We patch, reframe where needed, and bring outlets up to code before any new box goes in. You approve any found-condition changes in writing at this point, with a fixed number, before we continue.
Stage 3: Cabinet install (days 5 – 7)
Base cabinets set first, then uppers, shimmed and scribed to the wall. A laser level at this stage is the difference between doors that close flush and doors that catch. You make your final pull, hinge, and drawer-slide selections in advance of this stage; soft-close undermount slides and full-extension drawers are the standard we install unless you specify otherwise. If you’re weighing a related job, homeowners often pair this with a Garage Conversion ADU in Westminster that also needs a small galley kitchenette built from the same cabinet order.
Stage 4: Countertop template and fabrication (days 8 – 14)
Once cabinets are locked in, template happens. That’s a physical measure on site, not off the drawing. Fabrication takes five to eight working days for quartz, longer for natural stone. You choose the slab, edges, and sink cutout before templating. Cambria quartz is what most of our Westminster buyers pick for its stain resistance and consistent look, and it holds up well to the daily cooking in multigenerational households.
Stage 5: Countertop set, backsplash, final walkthrough (days 15 – 18)
Counter goes down, seams are color-matched, sink and faucet get connected, and the backsplash gets set. Final walkthrough covers door alignment, drawer glide check, caulk lines, and a written punch list. Our 730-Day Done Right Promise covers workmanship from that point forward: if a door sags or a seam lifts, we come back and fix it.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The options you’ll actually choose between
Most decisions come down to four or five real forks. Here’s what each costs you in money and in patience.
- Reface or replace. Refacing keeps your existing boxes and runs roughly a third the cost of new cabinets. It only works if the boxes are solid and the layout stays. Replace if you’re changing the footprint or the cabinets are beyond repair.
- Stock vs semi-custom cabinets. Stock comes in fixed sizes and ships faster; semi-custom lets you fit an awkward corner or a nonstandard height. Kitchen ceiling heights in Westminster’s older one-story homes often run shorter than stock upper cabinet runs, so semi-custom is sometimes the only clean fit.
- Quartz vs granite vs porcelain slab. Quartz is the standard pick: non-porous, consistent pattern, no sealing. Granite is natural and heat-tolerant but needs sealing every year or two. Porcelain slab handles heat and scratches beautifully but chips at edges under impact. KraftMaid cabinetry paired with Cambria quartz is the combination we install most here.
- Edge profile. Eased and bullnose are standard and included. Waterfall edges and thick miters add cost and are worth it only if the island or peninsula is a focal point.
- Sink type. Undermount is standard; farmhouse apron-front sinks require a specific cabinet box and prep, and add a step to the cabinet build. Decide before cabinets are ordered, not after.
What Cabinets & Countertops costs in Westminster, CA

A full cabinet and countertop replacement in Westminster lands between $14,000 and $45,000. Cabinets alone run $4,000 – $13,000, countertops $2,000 – $6,500, and a backsplash $800 – $2,500. Here’s the line-item view.
| Line item | Westminster range |
|---|---|
| Cabinet installation (or refacing) | $4,000 – $13,000 |
| Countertop installation | $2,000 – $6,500 |
| Backsplash | $800 – $2,500 |
| Island install, if included | $3,000 – $10,000 |
| Full combined job | $14,000 – $45,000 |
Four things push a job toward the high end: cabinet linear footage (galley kitchens sit low, L-shaped and U-shaped sit high), whether plumbing or electrical has to move (relocating a sink or adding a dedicated circuit for a range adds real cost), the slab grade you pick, and found conditions behind the walls. Permits add a modest fee on top, typically pulled when electrical or plumbing changes or when walls come down.
A written estimate from us lists cabinet brand and door style, countertop material and edge profile, backsplash material, permit cost, demo, and haul-away. It does not include appliances unless you ask, and it doesn’t cover structural changes found after demo. Any change order requires your signature and a fixed number before work continues. That’s how no-hassle upfront pricing works: the number you see is the number you pay unless you approve a change.
See the difference
Before
After
Before
After
Before
AfterWhat Westminster homes specifically do to this job
Westminster’s housing stock is mostly 1950s – 1970s single-story stucco tract homes and low-slung commercial strips, and that build era changes what a cabinet job actually involves. Along Bolsa Avenue and through Little Saigon, we regularly pull cabinet boxes and find original galvanized plumbing that’s choked to half its interior diameter, or two-wire electrical with no equipment ground. Both need addressing before new cabinets go back in, or you’ll be tearing out the new work in a year to fix what should have been fixed the first time.
The permitting side has its own rhythm here. In occupied commercial remodels along Bolsa, work phases around operating hours, and Vietnamese signage and ventilation code requirements come into play. Residential work moves faster, but we still pull permits when electrical, plumbing, or structural scope triggers them, and we coordinate the inspection schedule with the city so you’re not sitting on a half-finished kitchen waiting for a callback. Marine layer humidity near the coast also affects how paint and stucco cure, so we plan finish coats around weather rather than fighting it. If the project grows into a wider scope, our Kitchen Remodeling in Westminster page covers the full-service version, including demolition sequencing and layout changes.
For Westminster residents thinking bigger, the same trades come into play whether you’re updating one kitchen or building a New Detached ADU in Westminster with its own kitchenette. The cabinet and countertop choices you make for the main house often inform what you spec for the ADU, and buying them together can save on fabrication and delivery.
Serving Westminster, CA – Our Local Coverage Area
We serve Westminster and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – Cabinets & Countertops in Westminster

Two to four weeks for a full cabinet and countertop replacement, with countertop fabrication as the longest single stage at five to eight working days. Refacing alone can compress to about a week. Call (833) 522-5059 for a schedule specific to your kitchen.
Only if the scope includes electrical, plumbing, or structural changes. Straight cabinet and counter swaps typically don’t trigger a permit, but relocating a sink, adding a circuit, or removing a wall does. We pull the permit and coordinate the inspection when required, and we’ll tell you upfront which side of that line your job falls on.
Yes, and that’s the majority of jobs we do. If the sink stays where it is and no walls move, the work is contained to cabinets, counter, and backsplash. Moving a sink or range hood vent typically adds two to four days and real cost, so it’s worth deciding early.
Full cabinet and countertop work runs $14,000 – $45,000, with cabinets alone $4,000 – $13,000 and counters $2,000 – $6,500. Your exact number depends on linear footage, material grade, and found conditions. Call (833) 522-5059 and we’ll get you a fixed written estimate on site.
Every cabinet and countertop job we install is covered by our 730-Day Done Right Promise: if something isn’t right, we make it right. Manufacturer warranties on KraftMaid cabinets and Cambria quartz run separate and stack on top. Call (833) 522-5059 to talk through the details before you commit.
Get a free estimate for your Westminster cabinets and counters
Call (833) 522-5059 for a free on-site estimate. We’ll measure, check what’s behind the existing boxes, and hand you a written line-item number the same visit: cabinets, counters, backsplash, permits, and demo all spelled out. No change orders without your signature. Calls are answered by a live person, and our technicians arrive background-checked and in uniform. If the scope grows, we’re set up for both Kitchen Remodeling and cabinet-only jobs, and we cover every ZIP in Westminster.
Written by the team at Groundwork Construction Co. of Buena Park.